Board of Trustee Minutes
CHARTER TOWNSHIP OF BLOOMFIELD
BOARD OF TRUSTEES
Study Session
September 6, 2007
PRESENT: Supervisor Payne, Clerk Roncelli, Treasurer
Devine; Trustees Stefanes, Buckley, Barnett, and Savoie
Also present, Police Chief Bowden, Fire Chief Chartier, Tom
Trice, Public Works Director, Christine Tvaroha, Senior
Services Director, Wayne Domine, Engineering & Environmental
Director, Gayle Sadler, IT Director, Ray Perkins, Finance
Director, Tom Marchesano, Capital Building Program Manager,
John Argenta, Project Architect, CDPA, Louis Margitan, Project
Architect, CDPA, Jim Pappas, Project Architect, Fusco, Shaffer
and Pappas, Dennis Smith, Construction Manager, Auch
Construction
Capital Building Program Update:
The presentation reviewed the project scope and budget. At
the meeting on July 24, 2007, there were concerns regarding
the renovations being proposed to the central fire station.
Several meetings were conducted with the bonding attorney and
administration. It was determined that the lower level of the
fire station would be refurbished and the upper level
completely rebuilt.
DPW Building:
The proposed renovation has been reviewed with staff
members and appears to be a viable solution. The building was
reconfigured into an "L" shape due to bad soil and it was
decided that the building footprint would be smaller, but
there would be no compromise on function.
The second level was removed and these rooms were moved to
the basement. This enabled a two-story building to become
one-story with a partial basement, which saved money.
The cell tower will be maintained and will stay in
service;this will eliminate sequencing traumas while work is
being done which will be cost effective.
The Emergency Operating Center (EOC) was relocated to the
basement of the DPW building instead of the central fire
station. The garage will hold 35 large trucks and also
additional vehicles in the middle if necessary. Also, six
heavy-duty repair bays with three lifts and three light duty
bays will be housed in the garage.
Parts of the existing DPW building will be kept. There will
still be ample parking and adequate ingress/egress access.
Improvements for the police parking lot include paving and
carports.
The Road department will be renovated for grounds
equipment. Documentstorage will be moved to the upper level
and storage of election records will be moved downstairs. The
tower equipment room will remain with existing parts to be
refurbished.
Central Fire Station:
Storage remains a major issue with the current fire station
design. Storage rooms, a workroom and EMS storage will be
added to the upper level. The administration offices are very
small as a stairway prevents good circulation. The proposed
design will move the stairway, which will allow for the two
assistant chiefs’ offices to be the same size. The conference
room and administrative assistant’s office will be moved. A
patio will be added to the living area. Stairs, doors and
windows will be added to the hose tower to allow for adequate
training.
Renovations to the lower level will improve circulation on
this floor. There will be increased room for the Fire Marshal
and inspectors. The current garage will now be the training
room and new roofs will be installed. There will be restrooms
on the upper and lower levels.
Senior Services:
The new design proposes an access point off Andover, across
from the Echo Park entrance.
The Senior Services parking lot and the 48th District Court
parking lot will be separated by a gate, which can be opened
to allow for additional parking during special events. The
gate would be controlled by the Senior Center.
The new two-story building will be constructed on the south
side of the Township campus. The lower level will serve as the
active function area – fitness room, pool, and locker rooms.
Patios will be on this level off the exercise rooms.
The upper level (main floor) will have two central points
of access and the pool area will be viewable from this floor.
The "Meals on Wheels" program will also have a separate
entrance with a kitchen warming area. There will be two large
activity rooms that are designed for many uses. The senior day
care will also be located on this level. The day care will
have a separate entrance, activities area and outside area
that is secure. The building will contain as much glass as
possible on the southern side, providing a view of the woods
and wetlands.
The alternate plans for the Senior Services building moved
the fitness equipment to the middle of the walking track which
increased its size. The fitness rooms were relocated and a
single open stairway was created instead of an enclosed
stairwell.
Operating costs were discussed in regards to bigger
buildings having larger utility bills. These costs will be
incorporated into the department’s budget. Utility costs have
not been an issue in the past. Currently the DPW and central
fire station buildings lose a lot of energy due to old HVAC
units and poor insulation. The renovated buildings will
alleviate these concerns. The new DPW building will have more
windows, which will assist with lighting issues during the
day.
|
Proposed Estimates: |
| Westview
Fire Station - |
$
856,817.00 |
| Senior
Services - |
$
5,758,760.00 |
| Central
Fire Station - |
$
2,941,951.00 |
| DPW
Building - |
$13,593,261.00 |
| Police
Parking Lot - |
$
536,603.00 |
| Police
Rifle Range (if added at time of Construction) |
$
125,000.00 |
|
Subtotal Construction Cost - |
$23,812,392.00 |
| Owners
Direct Cost - |
$
4,800,000.00 |
| Total
Project Cost - |
$28,612,392.00 |
| Program
Budget - |
$26,000,000.00 |
| Over
Budget - |
- $
2,612,392.00 |
There are three categories that make up the Owners Direct
Costs: 1) Architects and engineers 2) Furniture and computer
costs 3) County fees, moving, temporary trailers for housing,
construction utilities, pre-construction services, Capital
Building Program Manger services, insurance, document
printing, soil boring, hazardous materials, project
construction costs and bond costs.
The project is almost three million dollars short of the
program budget. There are five areas from where this money
could be extracted:
Interest from the construction fund becomes a resource.
The project will take approximately two years to complete
and during that time the $26 million will be earning
interest. A very conservative estimate is $500,000.00, but
there is a good chance it could earn $1,000,000.00.
Capital expenditures could be used to defray some of
the cost for the police parking lot project.
Health Care – Premium Stabilization Reserve (PSR) can
be transferred to the General and Public Safety funds.
General Fund reserves (General and Public Safety Funds)
have a healthy balance of which $1,000,000.00 could be
assigned to the budget.
Senior Services is consistently under budget -
$300,000.00 could be utilized for this project.
Bond counsel advised the Board to sell the 26 million
dollars in bonds all at once if within a 26-month period.
It was determined that it is best to construct the police
rifle range now as opposed to later when cost would be higher.
Also, Westview Fire Station construction would start now, but
the other buildings would not begin until Spring 2008. This
will reduce winter construction costs.
MOTION by Barnett and SUPPORT by Stefanes to APPROVE the
Schematic Design Project as Presented.
Ayes: Barnett, Buckley, Devine, Payne, Roncelli, Savoie,
Stefanes
Nays: None
Meeting adjourned at 10:05 a.m.
__________________________
JANET RONCELLI
TOWNSHIP CLERK
dm
Home |
Government |
Services |
Community |
Current Events |
Resources
Contact Us |
E-mail List |
Forms
Still can't find what you're looking for?
Use our comprehensive Search or
Site Map pages!
Charter Township of Bloomfield
4200 Telegraph Road
P.O. Box 489
Bloomfield Hills, MI 48303-0489
248.433.7700
This site is best viewed in Internet Explorer
5.5 or higher and Netscape 6.0 or higher.
Having trouble accessing our site forms?
Your browser may not have the Acrobat Reader plug-in
that is required.
Click here to download a free copy of this software.
Site Design/Development